Posted by David Lesher on May 2, 2010, 11:29 pm
I'm looking for make/models of inverter systems that can work in
two different cases:
a) Grid-tie; when excess PV output is sold back to the utility.
b) Offline backup: When the grid's dead; you draw down on
battery backup, and/or generator.
While some folks talk about doing both in one box, it appears
both regulatory and technology issues generally preclude same,
at least in the 15KW/3ph. and up PV range.
Further, we want to take advantage of the PV capacity
whenever. In other words, in b) mode, we want the PV output to
supply loads, including battery recharge. Most of the vendors
I've looked at fall down in that regard.
(At first, I thought it could be done at the DC level, but no
joy there; the grid-tie inverters want DC strings in the hundreds
of volts; the stand-alone ones are expecting 48V or other lower
voltage DC inputs.)
Sunny/aka SMA tells me they can not only recharge the battery
plant from the PV inverter, but if the array can't keep up; it
will request a generator start and all three 60 Hz. sources will
play, in tune as needed.
So my questions:
1) Has anyone here used such a system?
2) Know of any other venders of such cooperative systems?
Posted by sspence on May 3, 2010, 1:05 pm
> I'm looking for make/models of inverter systems that can work in
> two different cases:
> a) Grid-tie; when excess PV output is sold back to the utility.
> b) Offline backup: When the grid's dead; you draw down on
> battery backup, and/or generator.
> While some folks talk about doing both in one box, it appears
> both regulatory and technology issues generally preclude same,
> at least in the 15KW/3ph. and up PV range.
> Further, we want to take advantage of the PV capacity
> whenever. In other words, in b) mode, we want the PV output to
> supply loads, including battery recharge. Most of the vendors
> I've looked at fall down in that regard.
> (At first, I thought it could be done at the DC level, but no
> joy there; the grid-tie inverters want DC strings in the hundreds
> of volts; the stand-alone ones are expecting 48V or other lower
> voltage DC inputs.)
> Sunny/aka SMA tells me they can not only recharge the battery
> plant from the PV inverter, but if the array can't keep up; it
> will request a generator start and all three 60 Hz. sources will
> play, in tune as needed.
> So my questions:
> 1) Has anyone here used such a system?
> 2) Know of any other venders of such cooperative systems?
Outback makes a line of gridtie with battery backuo inverters. I've
installed many of them.
http://www.outbackpower.com/products/sinewave_inverter/grid_tie/
Steve Spence
http://www.green-trust.org
Posted by You on May 3, 2010, 6:43 pm
In article
> Outback makes a line of gridtie with battery backuo inverters. I've
> installed many of them.
>
> http://www.outbackpower.com/products/sinewave_inverter/grid_tie/
>
> Steve Spence
> http://www.green-trust.org
Yep, Outback is your Friend... If you want 15Kw/or larger Grid-Tie with
Battery backup, and PV Charging with Genset backup...
Posted by sspence on May 4, 2010, 10:18 am
> In article
> > Outback makes a line of gridtie with battery backuo inverters. I've
> > installed many of them.
> >http://www.outbackpower.com/products/sinewave_inverter/grid_tie/
> > Steve Spence
> >http://www.green-trust.org
> Yep, Outback is your Friend... If you want 15Kw/or larger Grid-Tie with
> Battery backup, and PV Charging with Genset backup...
Outback starts at 3.5kw and is stackable for larger wattages.
Posted by David Lesher on May 4, 2010, 1:02 am
>Outback makes a line of gridtie with battery backuo inverters. I've
>installed many of them.
>http://www.outbackpower.com/products/sinewave_inverter/grid_tie/
Thanks; I've looked at them, but thus far, I've not found any
reference to 3ph deployments. I do find it interesting that
they claim it's both grid-tie and backup; PGE insists that can
not be in their world.
I'm still researching....
--
A host is a host from coast to coast.................wb8foz@nrk.com
& no one will talk to a host that's close........[v].(301) 56-LINUX
Unless the host (that isn't close).........................pob 1433
is busy, hung or dead....................................20915-1433
> two different cases:
> a) Grid-tie; when excess PV output is sold back to the utility.
> b) Offline backup: When the grid's dead; you draw down on
> battery backup, and/or generator.
> While some folks talk about doing both in one box, it appears
> both regulatory and technology issues generally preclude same,
> at least in the 15KW/3ph. and up PV range.
> Further, we want to take advantage of the PV capacity
> whenever. In other words, in b) mode, we want the PV output to
> supply loads, including battery recharge. Most of the vendors
> I've looked at fall down in that regard.
> (At first, I thought it could be done at the DC level, but no
> joy there; the grid-tie inverters want DC strings in the hundreds
> of volts; the stand-alone ones are expecting 48V or other lower
> voltage DC inputs.)
> Sunny/aka SMA tells me they can not only recharge the battery
> plant from the PV inverter, but if the array can't keep up; it
> will request a generator start and all three 60 Hz. sources will
> play, in tune as needed.
> So my questions:
> 1) Has anyone here used such a system?
> 2) Know of any other venders of such cooperative systems?